Our Projects

Rail - Construction - Utility

PROJECTS

\

CMSD Smarter Isolations Project – Phase 2 Wessex

Supply of Electrical Site Managers, Supervisors, Electricians and Electrical Mates. The works entail cable pulling, cable dressing, cable terminations; all control and indication wiring/LV cabling/ DC cabling/SCADA, building of marshalling panels and boxes.

\

CMSD Smarter Isolations Project Phase 1 & 2 – Southeast

Supply of civils route works installation team installing Concrete bases and hard standings, GRP raised route, concrete troughing routes, cable pulling.

\

Emergency Works – Streatham LVAC Replacement

Emergency replacement of burnt out LVAC panel at Streatham Substation. We worked collaboratively with the client and Network Rail to mobilise with short notice and to ensure all materials, documentation and resource was arranged.

\

Grove Park Depot

Installation and commissioning of LCS 750v DC circuit breaker, installation and testing of LV equipment including 110v 32A welding transformers, klaxon warning beacons, overhead status indicators, emergency stop push buttons, 110v supply for inspection & testing, power supply for roller shutter and lighting & small power.

\

Gospel Oak to Barking

Installation and termination of 650v signalling cable, OHLE bonding works, installation and termination of DNO, points heating and infrastructure equipment.

\

Reading 10 car

Electrical installation and commissioning at Buckhurst TP Hut. Conversion of TP Hut to a fully operational Substation including all control and indication wiring in HV module and then commissioning the HV module into service, installation and commissioning of the Auxiliary transformers and LVAC panel, all SCADA communication wiring and commissioning the new RTU into operational service, install Frame leakage relays and complete wiring modifications to existing 750v DC RJR circuit breakers, test and commission new substation earth system and installation of all control and indication wiring to 3MW transformer and Rectifier module.

\

GWEP

Civils installation team installing concrete bases and hard standings, GRP raised route, concrete troughing routes, buried route and cable pulling.

\

Crossrail West

Installation, jointing and termination of 650v signalling cable, DNO and infrastructure equipment terminations along with cable pulling.

\

Reading TVA Project

Installation, jointing and termination of 650v signalling cable, DNO and points heating equipment terminations along with cable pulling.

\

DC Transport

Supply of 2-man teams to dig out, lay utility ducting, backfill and reinstate. Installation of Chamber/Footway/Stakka boxes. Carry out cable pulling and fibre splicing.

\

GEML PSU

Supply of Management, Safety Critical staff and up to 40 PTS cable pullers to install fibre and copper cables to connect up the SCADA and Telecommunications for a new HV Substation.

\

GEML PSU

Minor civil ancillary package, installation of URX, installation of cable trough route, installation of concrete ballast board, concrete repairs to foundations and installation and refurbishment of access road.

\

Catford Station, Westdown Road Bridge

Bought in to carry out the disconnections and re-connections of the DOO, PA and Lighting columns on the station platform that was being replaced due to a new bridge structure. Commissioning of the DOO camera including supplying Telecoms TIC & CRE for the Test Plan.

\

Sussex PSU

Negative cable installation/terminations at Queens Road Substation, our scope included the installation of GRP ladder racking, concrete troughing installation, ETE cable terminations at both track and negative busbar and all supervised by Level A T&C.

\

Reading 10 Car Pilot

Installation/jointing of pilot cables at 3 sites to remove redundant pilot boxes in TP Huts.

\

Contingent Labour

Every week and weekends we are supplying our clients with labour for their works, the labour skill set various from PTS Labourers, PTS Skilled Trackmen, LXA’s, PO’s, COSS/SWL1, CC/MC’s, ES/SWL2, HV Comps and Level A T&C staff.

.